The last phase of our resurfacing project on Textile Rd in Pittsfield & Ypsilanti Townships is quickly moving along!
Earlier today, the contractor was able to mill the existing surface of Textile Rd between Cayman Blvd and Munger Rd in Pittsfield Township, as well as a patch of Textile Rd just east of Whittaker Rd in Ypsilanti Township. The contractor expects to pave both sections of Textile Rd tomorrow. Last steps will be placing aggregate (stone) shoulders and pavement markings!
The Washtenaw County Road Commission (WCRC) will continue to send out updates as the project progresses. Have questions? Contact Mike Bernbeck, project manager, at (734) 327-6654, or via email at [email protected].