WHEN: Friday, August 4, 2017 WHERE: Clinton Road between Austin Road and County Line in Bridgewater Township WHY: Installation of Centerline Corrugations BACKGROUND: On Friday, August 4, 2017, the Washtenaw County…
WHEN: Wednesday, August 2, 2017 WHERE: Currie Road between Five Mile Road and Six Mile Road in Salem Township WHY: Culvert Replacement Complete BACKGROUND: On Wednesday, August 1, 2017, Washtenaw…
WHEN: Monday, August 7, 2017 until further notice WHERE: Six Mile Road between Main Street and Nollar Road in Northfield Township WHY: Culvert Replacement at the Horseshoe Lake Drain BACKGROUND:…
We are rounding third base and heading home! We applied the final asphalt course on Monday, July 31. Driveway approaches and slope restoration (seed, grass, fertilizer, mulch) will be completed…
WHAT: Public Meeting Regarding the 2018 Baker Road Intersection Improvement Project WHEN: Tuesday, August 15, 2017 at 6 pm WHERE: Creekside Intermediate School at 2615 Baker Rd, Dexter, MI…
WHEN: Friday, July 28 at 7 pm through Saturday, July 29 at 8 am WHERE: US-12 between Moon Rd/State Rd and S. Industrial Dr in Pittsfield Township WHY: Culvert Replacement…
Concrete work was completed last week. The first layer of pavement will be laid the afternoon of Tuesday, July 25. Before the top course of asphalt is applied, ditches will…
WHEN: Tuesday, July 25, 2017 WHERE: Huron River Drive between Chalmers Drive and Hogback Road in Ann Arbor Township WHY: Bridge Repairs BACKGROUND: On Tuesday, July 25, 2017, a Contractor…
WHEN: Thursday, July 20, 2017 WHERE: Pleasant Lake Road between Parker Rd and Zeeb Rd in Lodi Township WHY: Culvert Replacement Complete BACKGROUND: On Thursday, July 20, 2017, Washtenaw County…
The work performed on this bridge includes concrete deck repairs, deck joint replacement and beam painting. Work remaining to be completed includes guardrail replacement and an epoxy overlay on the…