Project Update #7: N. Territorial Rd & Webster Church Rd Safety Improvements (Webster Twp)

We’re paving our safety project taking place at the intersection of N. Territorial Rd & Webster Church Rd in Webster Township!

Since the last update, the contractor placed the aggregate (stone) road base and paved two courses (layers) of asphalt on the southern side of the project limits. Currently, the contractor is working on ditching and placing the aggregate base for the curb and gutter on the north side of the project limits. The next step is to prepare for the traffic shift on N. Territorial Rd. Motorists should expect the north side lane to shift onto the (new) south side lane, with the same temporary traffic control signals in place, within the next week.

The Washtenaw County Road Commission (WCRC) will continue to send out updates as the project progresses. Have questions? Contact Becky Houle, Project Manager – Traffic & Safety, (734) 327-6678, or via email at [email protected].

Pictured above is the paving being performed at the intersection of N. Territorial Rd & Webster Church Rd in Webster Township.