Dino Dr

Location of roadwork:
Dino Dr south of Jackson Rd

Township:
Scio

When is the work being done:
2024

Description of work:
Pulverize & Rehabilitate

Impact on Traffic:
Lane Restrictions and Flagging Operation

Funding Source(s):
Michigan Transportation Fund (MTF), Scio Township Downtown Development Authority

Latest Updates

October 16, 2024 Project Update #3: Dino Dr (Scio Twp)

This week, the contractor for the Washtenaw County Road Commission (WCRC) laid the final layer of hot mix asphalt on Dino Dr between Jackson Rd and the cul-de-sac in Scio Township. Crews recently placed aggregate stone shoulders.  

Have any questions about this project contact Mike Bernbeck, Project Manager – Design & Construction, (734) 327-6654, or via email at [email protected]. 

Pictured above new pavement on Dino Dr between Jackson Rd and the cul-de-sac in Scio Township. 
October 2, 2024 Project Update #2: Dino Dr (Scio Twp)

The contractor for the Washtenaw County Road Commission (WCRC) crushed and shaped (pulverized) the old asphalt on Dino Dr between Jackson Rd and the cul-de-sac in Scio Township. Next steps are to place two layers of hot mix asphalt along Dino Dr this week, weather permitting. 

Motorists can expect lane restrictions in the work zone.  

WCRC will continue to send out updates as the project progresses. Have questions? Contact Mike Bernbeck, Project Manager – Design & Construction, (734) 327-6654, or via email at [email protected] 

Pictured above pulverized pavement on Dino Dr between Jackson Rd and the cul-de-sac in Scio Township. 
September 23, 2024 Lane Restrictions: Dino Dr (Scio Twp)

WHEN: Monday, September 30, 2024

WHERE: Dino Dr between Jackson Rd and the cul-de-sac in Scio Township

WHY: Road resurfacing

BACKGROUND: On Monday, September 30, 2024, the Washtenaw County Road Commission (WCRC) will begin a resurfacing project on Dino Dr between Jackson Rd and the cul-de-sac in Scio Township.

The road will not be closed to traffic, but delays are likely due to daily lane restrictions.

The road improvements are expected to take approximately two weeks to complete. However, all dates are tentative and subject to change due to weather conditions.

CONTACT: If you have any questions concerning this work, please contact Mike Bernbeck, Project Manager – Design & Construction, (734) 327-6654, or via email at [email protected]

ISSUE DATE: 09/23/24

September 20, 2024 Project Update #1 – Dino Dr (Scio Twp)

A road resurfacing project is scheduled to begin on Dino Dr between Jackson Rd and the cul-de-sac in Scio Township. A contractor for the Washtenaw County Road Commission (WCRC) plans to pulverize the existing road, then place two layers of hot mix asphalt along Dino Dr. This work is anticipated to begin the week of September 30, 2024.  

Motorists can expect lane restrictions in the work zone. The project is expected to take approximately two weeks to complete, weather permitting.  

WCRC will continue to send out updates as the project progresses. Have questions? Contact Mike Bernbeck, Project Manager – Design & Construction, (734) 327-6654, or via email at [email protected] 

Pictured above old pavement on Dino Dr between Jackson Rd and the cul-de-sac in Scio Township. 
Contact information:
Felix Weber-Bailey
    • (734) 327-6689
Helpful Links
Receive Updates on the Project
Subscribe to Project Updates