Location of roadwork:
Intersection of Whittaker Rd at Willis Rd
Township:
Augusta
When is the work being done:
June 3, 2024
Description of work:
Roundabout
Impact on Traffic:
Intersection Closure with Detour
Funding Source(s):
Federal
Latest Updates
On Saturday, August 10, 2024, the contractor reopened the intersection of Whittaker Rd and Willis Rd in Augusta Township.
Since the last update, the contractor has placed permanent pavement markings and traffic lighting has been installed. In an effort to open the intersection to the public early, temporary signs have been placed with permanent signs being installed within the next two weeks. In addition, the contractor will be finalizing minimal surface work and completing restoration.
The Washtenaw County Road Commission (WCRC) will continue to send out updates as the project progresses. Have questions? Contact Kevin Dubnicki, Project Manager – Design & Construction, at (734) 327-6693, or via email at [email protected].
WHEN: Saturday, August 10, 2024
WHERE: Intersection of Whittaker Rd and Willis Rd in Augusta Township
WHY: Complete: roundabout construction
BACKGROUND: On Saturday, August 10, 2024, the Washtenaw County Road Commission (WCRC) reopened the intersection of Whittaker Rd and Willis Rd in Augusta Township.
CONTACT: If you have any questions concerning this work, please contact Kevin Dubnicki, Project Manager – Design & Construction, (734) 327-6693, or via email at [email protected]
ISSUE DATE: 08/12/24
Our roundabout project at the intersection of Whittaker Rd & Willis Rd in Augusta Township is one step closer to the finish line!
Since the last update, the contractor has been able to pave the leveling course (first layer of asphalt) and the wearing course (last layer of asphalt) throughout the roundabout. Next step is placing permanent pavement markings and installing signs. Once this work is complete the intersection will re-open to all traffic.
The Washtenaw County Road Commission (WCRC) will continue to send out updates as the project progresses. Have questions? Contact Kevin Dubnicki, Project Manager – Design & Construction, at (734) 327-6693, or via email at [email protected].
Pictured is the new asphalt surface of the roundabout at Whittaker Rd at Willis Rd in Augusta Township.
Our roundabout project at the intersection of Whittaker Rd and Willis Rd in Augusta Township is making steady progress.
Since the last update, the contractor has been able to construct concrete curb and gutter and place red concrete in the roundabout islands. While the contractor allows the concrete to cure, preparations for asphalt paving are taking place. The contractor plans to begin paving by July 29, weather permitting. Once paving is complete, pavement markings and signs will be installed.
As a reminder, the intersection remains closed to the traveling public. Please refrain from entering the project limits as construction for the roundabout continues.
Have questions about the project? Contact Kevin Dubnicki, Project Manager – Design & Construction, at (734) 327-6693, or via email at [email protected].
The Washtenaw County Road Commission (WCRC) roundabout project taking place at the intersection of Whittaker Rd and Willis Rd in Augusta Township is going well!
Over the past week, the contractor has been successful in the installation of the storm drain and underdrain required for proper removal of water from the roadway surface. The aggregate base (sub layer) for the roadway is being placed and expected to be leveled by the end of the weekend. However, recent rain events could delay progress until things dry out. The contractor plans to begin pouring concrete for the curb lines the week of July 15.
The intersection of Whittaker Rd and Willis Rd remains closed to the traveling public. Access will only be maintained for residents who live or work within the construction zone.
WCRC will continue to send out updates as the project progresses. Have questions about the project? Contact Kevin Dubnicki, Project Manager – Design & Construction, at (734) 327-6693, or via email at [email protected].
Pictured above is Willis Road facing east. The roundabout is taking shape!
Our roundabout project at the intersection of Whittaker Rd and Willis Rd in Augusta Township is making great progress!
Since the last update, utility relocations were completed throughout the project limits. Construction for the roundabout began June 17. The existing pavement has been crushed and the contractor is working to install the storm sewer and perform other necessary drainage work. Next, the contractor will begin placing the road base in preparation for the new road surface and installing concrete curb & gutter.
The intersection of Whittaker Rd and Willis Rd remains closed to the traveling public. Access will only be maintained for residents who live or work within the construction zone. The Washtenaw County Road Commission (WCRC) will continue to send out updates as the project progresses. Please be courteous and do not drive through school property as numerous reports are being made of public traveling across grass and sidewalks within the school property attempting to bypass the construction.
Have questions about the project? Contact Kevin Dubnicki, Project Manager – Design & Construction, (734) 327-6693, or via email at [email protected].
Construction operations related to the Whittaker Rd & Willis Rd Roundabout project in Augusta Township are underway!
On June 3rd, the intersection was closed to traffic to allow for utility relocations in preparation for the roundabout construction. The utility relocations are expected to take approximately two weeks. The roundabout construction is expected to start on or about June 17, 2024. The Washtenaw County Road Commission (WCRC) will continue to send out updates as the project progresses.
Motorists are advised to seek an alternate route. The intersection closure is in place to promote motorist and construction worker safety and provide for the efficient completion of work.
Have questions? Contact Kevin Dubnicki, Project Manager – Design & Construction, (734) 327-6693, or via email at [email protected].
WHEN: Monday, June 3, 2024
WHERE: Intersection of Whittaker Rd and Willis Rd in Augusta Township
WHY: Roundabout construction
BACKGROUND: On Monday, June 3, 2024, the Washtenaw County Road Commission (WCRC) will close the intersection of Whittaker Rd and Willis Rd in Augusta Township to begin roundabout construction.
The road improvements are expected to take approximately 12 weeks. However, all dates are tentative and subject to change due to weather conditions.
DETOUR: Click here for the detour map.
CONTACT: If you have any questions concerning this work, please contact Kevin Dubnicki, Project Manager – Design & Construction, (734) 327-6693, or via email at [email protected]
ISSUE DATE: 05/29/24
WHEN: Monday, March 4, 2024
WHERE: Intersection of Whittaker Rd and Willis Rd in Augusta Township
WHY: Forestry
BACKGROUND: On Monday, March 4, 2024, a contractor for the Washtenaw County Road Commission (WCRC) will begin forestry work at the intersection of Whittaker Rd and Willis Rd in Augusta Township.
The road will not be closed to traffic, but delays are likely due to lane restrictions. WCRC encourages motorists, emergency services and others to use an alternate route.
The forestry work is expected to take approximately three days. However, all dates are tentative and subject to change due to weather conditions.
CONTACT: If you have any questions concerning this work, please contact Nate Murphy, Sr. Project Manager – D&C, (734) 327-6647, or via email at [email protected]
ISSUE DATE: 02/29/24
During the 2024 construction season, the Washtenaw County Road Commission (WCRC) plans to construct a roundabout at the intersection of Whittaker Rd and Willis Rd in Augusta Township. The intersection will be closed to all traffic during construction and a detour will be posted.
Thank you to those who were able to attend our virtual public construction information meeting on Thursday, February 22, 2024. If you weren’t able to join us, click here to watch the meeting recording or check out the slide show. WCRC will continue to send out updates as the project progresses.
Questions about the project? Contact Nate Murphy, project manager, at (734) 327-6647, or via email at murphyn@wcroads.org.
PROJECT: Whittaker Rd at Willis Rd Roundabout Project
WHEN: Thursday, February 22, 2024, at 12 p.m.
WHERE: Online: https://bit.ly/wcrcprojectmeeting
By Touchtone Phone: (929) 205-6099, Meeting ID: 879 2332 8754
WHY: The Washtenaw County Road Commission (WCRC) will hold a virtual project information meeting regarding the roundabout at the intersection of Whittaker Rd and Willis Rd in Augusta Township.
During construction, the intersection of Whittaker Rd and Willis Rd will be closed to ALL traffic and a detour will be posted. The closure is expected to be in place for approximately 11 weeks, weather pending.
The virtual public meeting will be held via Zoom on Thursday, February 22, 2024, at 12 p.m. There will be a brief presentation followed by time for questions from the audience. A recording of the meeting will be posted to the project web page after the meeting.
Click here to learn more about joining the virtual meeting.
CONTACT: If you have any questions concerning this project, please contact Nate Murphy, project manager, at (734) 327-6647, or via email at [email protected].
WCRC will provide necessary reasonable auxiliary aids and services, such as signers for the hearing impaired and audiotapes or printed material being presented at the meeting, to individuals with disabilities upon a 5-business day notice. Individuals with disabilities requiring auxiliary aids or services should contact Tiffany Oliphant, communications manager, by phone (734) 327-6646 or by email [email protected].
ISSUE DATE: 01/24/24
During the 2024 construction season, the Washtenaw County Road Commission (WCRC) plans to construct a roundabout at the intersection of Whittaker Rd and Willis Rd in Augusta Township. The intersection will be closed to all traffic during construction and a detour will be posted.
Thank you to those who were able to attend our virtual public design information meeting on Thursday, November 2, 2023. If you weren’t able to join us, click here to watch the meeting recording or check out the slide show. WCRC plans to hold a construction information meeting closer to the start of construction. WCRC will continue to send out updates as the project progresses.
Questions about the project? Contact Nate Murphy, project manager, at (734) 327-6647, or via email at murphyn@wcroads.org.
PROJECT: Whittaker Rd at Willis Rd Roundabout project
WHEN: Thursday, November 2, 2023, at 11:30 a.m.
WHERE: Online: https://bit.ly/wcrcprojectmeeting
By Touchtone Phone: (929) 205-6099, Meeting ID: 879 2332 8754
WHY: The Washtenaw County Road Commission (WCRC) will hold a virtual project information meeting regarding the roundabout project planned for the intersection of Willis Rd and Whittaker Rd in Augusta Township.
During construction, the intersection of Willis Rd and Whittaker Rd will be closed to all traffic. The closure is expected to be in place for 10 weeks, weather pending.
The virtual public meeting will be held via Zoom on Thursday, November 2, 2023, at 11:30 a.m. There will be a brief presentation followed by time for questions from the audience. A recording of the meeting will be posted to the project web page after the meeting.
Click here to learn more about joining the virtual meeting.
CONTACT: If you have any questions concerning this project, please contact Nate Murphy, project manager, at (734) 327-6647, or via email at [email protected].
WCRC will provide necessary reasonable auxiliary aids and services, such as signers for the hearing impaired and audiotapes or printed material being presented at the meeting, to individuals with disabilities upon a 5-business day notice. Individuals with disabilities requiring auxiliary aids or services should contact Tiffany Oliphant, communications manager, by phone (734) 327-6646 or by email [email protected].
ISSUE DATE: 09/26/23